What happened in Sister Bay
This Sister Bay job was approved as private work, and the crew documented it with 12 photos on October 5, 2026.
The crew went up through the ceiling hatch into an attic filled with loose blown-in insulation. They dug down through the insulation in several spots and set a moisture meter on the ceiling drywall and the framing underneath, photographing each reading. Wet insulation and drywall above a ceiling can stay hidden for a long time because the insulation covers it.
At the time of the visit, part of the building's roof was covered with a tarp.
Work performed
- Attic access through the ceiling hatch
- Insulation dug back at several spots
- Moisture readings on the ceiling drywall and framing