What happened in Fort Howard
This mold remediation and build-back job is in the Fort Howard area of Green Bay. The project was first opened in CompanyCam in June 2023 and has 152 photos. The photos here are from September 2025.
On September 4 the garage ceiling was partly open along one side, with tools and yard equipment hung on the wall below. Inside the house, a room next to the patio door had its flooring removed down to the subfloor, with old adhesive and stains still on it.
Over the next two weeks the garage was rebuilt. New drywall went up on the ceiling and the upper walls, and by September 15 the seams and corners had been taped and coated with joint compound, ready for sanding and paint. The photos look up into each corner where the ceiling meets the walls so the finish work is on record.
Work performed
- Mold remediation
- Flooring removed in the room by the patio door
- Garage ceiling opened
- New drywall taped and mudded in the garage
Photos labeled Before and After were taken by the CCS crew on this job.