What happened in Sister Bay
This Sister Bay job combined mold remediation with build-back. It was opened on July 1, 2026, and the crew logged 85 photos. The ones here are from August 19 and October 1.
The August photos show the basement walls opened up: the lower drywall cut out around the finished rooms, and in some sections the wall taken down to the studs with the insulation exposed. A doorway was sealed with plastic sheeting to contain the work area. The unfinished side shows pink insulation along the rim joists.
The October photos show the same walls closed back up, with new drywall finished smooth at the base.
Work performed
- Lower drywall cut out in the finished rooms
- Walls opened to the studs in sections
- Plastic containment at the doorway
- Mold remediation
- New drywall installed and finished