What happened in Green Bay
This Green Bay job was approved for mold remediation at the end of June 2026. The crew logged 63 photos, and the ones here are from September 4.
A section of ceiling over the dining area had been opened, and one photo looks up into the cavity, where the wood framing shows dark staining. The rest of the set covers the bathroom: the toilet, the vanity and the floor, including a close shot of the gap where the wood floor meets the bathroom flooring. The kitchen and living areas were photographed as well.
Together the photos record the condition of each room on the September visit.
Work performed
- Ceiling opened over the dining area
- Inspection of the framing in the ceiling cavity
- Bathroom floor and fixtures checked
- Mold remediation