What happened in Hobart
This Hobart job started as a water emergency on August 3, 2026 and moved into build-back. The crew logged 101 photos, and the ones here are from October 22, during the rebuild.
The room is being painted. The floor is covered with protective paper, a ladder stands in the middle of the room, and painter's tape protects the wood trim along the stairway. The photos show the ceiling and the light blue walls, with the corners and the angled ceiling by the stairs photographed up close.
Painting is usually one of the last steps before the floor protection comes up and the room goes back into use.
Work performed
- Water emergency response and drying
- Build-back of the affected room
- Ceiling and walls painted
- Floor and trim protected during painting